Specifications include, but are not limited to: The following are the items to be addressed as part of the scope of this project: -POOL- • Removal of existing coping stones. • Partially demolish the existing concrete deck around the pool perimeter. • Place additional gutter pipe and extend to the surge tank. • Build up the existing gutter walls. • Waterproof the existing gutter. • Pour new deck surface. • Extend the pool liner up the pool wall. • Install new coping stones. • Install handrails, grabrails, and any other ADA items. • Install both depth marker and NO DIVING tiles. • Level the zero-entry floor as needed. • Bonding of all metal objects in and around the pool. • Clean up after project completion. -PUMP ROOM- The following items are to be purchased and installed: • 1-Aquify Regenerative Media Filter 1600 sf-FRP PMF-60-1600-FRP • 1-Aquify PMF Suite D8 - 12in x 10in x 6in PMF-SUITE-D8 • 1-Aquify Strainer 12in x 12in STR-1212-FRP • 1-Aquify Strainer Basket 10in - 12in for FRP STR-BSK-C-FRP • 1-Aquify Tee 12in x 8in x 6in FRP TEE-120806-FRP • 1-Herborner F-N Pump 40HP NEMA motor FN150-270B-4004N-W2B • 1-Aquify Variable Frequency Drive 40HP 480v N4 with disconnect switch VFD4-D040-N4 • 1-Aquify Concentric Reducer 10in x 6in FRP RDC-1006-FRP • Update of all necessary plumbing and electrical. • New outdoor enclosure for chlorine storage tanks and equipment.