Specifications include, but are not limited to: Furnish labor to remove the existing 125 KW generator from the central plant yard. Generator will be craned off and given to Contractor if the credit is accepted. If the credit is not accepted the Contractor will move the generator to CSN designated area. Furnish labor and material to demo existing Generac ATS switch. 3.1. Furnish labor and material to reform pad as needed to accommodate new Standby generator. An alternate bid line is added for the addition of a concrete containment berm. CSN reserves the right to reject the alternate, whereby the best interests of CSN would be served. Existing conduits will be reused were applicable. New conduit and cabling will be provided where needed. Furnish labor and material for installation of (1) new CAT D125KW standby generator or equal. The existing underground conduit will be used to tie in new generator. Furnish labor and material for installation of (1) new 200 AMP ATS Switch. ATS Switch will be mounted on existing block wall adjacent to the generator. Existing conduits for power and low voltage will be reused as needed for controls and start wires to generator. Run new conduit and cable as needed. Fuel for the new diesel generator will be provided by CSN. Startup of new generator. Crane lifts need to be included in this proposal.