Specifications include, but are not limited to: The work contemplated consists of, but is not limited to the following major items as further defined in the Proposal Documents: · Furnishing, welding and installation of approximately 11 miles of HDPE Solid-Wall Pipe (28" down to 4"), welded side-saddle turnouts and delivery assemblies, · Furnishing and installing two pressure reducing assemblies · Associated mobilization, selective demolition, tree removal, trenching, earthwork, backfill, compaction, surface restoration, other restoration, · Coordination for utilities, utility relocations as necessary, coordination with Owner and Owner's Engineer and all other associated meter assemblies, stub turnouts, cleanouts, air and vacuum valve assemblies, valves and valve cans and appurtenances necessary to provide a complete project, ready for irrigation delivery.