Specifications include, but are not limited to: The selected firm shall provide construction inspection services for construction Contract B-41439. The anticipated Letting Date is February 15, 2024. The projected time period of need for construction inspection through substantial completion is estimated from April 1, 2024 through November 30, 2025. There is a early construction start date of March 1,2025. The CONSULTANT's personnel shall work under the INDOT Area Engineers or their designated representative. INDOT anticipates needing a total of 1 Project Engineer/Supervisor for 5,000 hours and 2 Project Inspectors for 5,000 hours each during the course of this Contract. It is expected that the majority of these hours will be incurred in 2025.