Specifications include, but are not limited to: 1) Remove and disposal or all parking lot debris i.e., old asphalt, dirt and trash generated from project. 2) Keep jobsite as clean as possible. 3) Dig adequate holes for new 6’ pole bases with a maximum of 30” above finished grade. The pole base will be 24” in diameter. See attached details for base and bolt pattern. A ground rod of 3/8”x 8’ with clamp is required at each pole base. 4) Dig adequate pipe trenches for a minimum of 18” below grade for new PVC pipe which will be 1 ¼” Schedule 40 PVC 5) Run 2 #6 ungrounded conductors (Black) and 1 #6 grounded conductor (Green) from power source Quazite box in parking lot. 6) Call 811 before any digging. 7) Obtain permits through the State for work to be inspected by State Electrical Inspector. 8) Assemble and install poles and fixtures. 9) Fill and patch parking lot/ seed and straw where needed. (Use of #9 gravel, with 2 inches asphalt base layer and 1.5 inch topping. Restripe to match existing. All other areas repair with like materials.) 10) Supply all materials.