Specifications include, but are not limited to: The contractor will be responsible for: • 3605 linear feet of ditch cleaning and shaping. • 40 linear feet culvert cleaning. • 10 linear feet culvert repair. • The Scope of work is marked with grade stakes and/or marking tape. • Ditches shall be cleaned and re-shaped to original grade in marked area. Anything over 5% grade shall be stone lined over filter fabric. See diagram at Attachment 1. • Slope failures, edge of road shall be rip-rapped and keyed in with stone. Establish a new toe of slope. See diagram at Attachments 2 & 3 • Repair of roadway to original grade. See diagram at Attachment 4. • The project completion date is October 31, 2023, unless any unforeseen problem warrants a time extension.