Specifications include, but are not limited to: project is split into two schedules, "Schedule 1" includes all water system work and "Schedule 2" includes all street construction work. The City may eliminate Schedule 2 work if weather conditions do not permit asphalt paving. Schedule 1 includes, but is not limited to, all labor, materials, and equipment necessary to construct approximately 600 lineal feet of 8-inch D.I. pipe, 45 lineal feet of 6-inch D.I. pipe, 180 lineal feet of 1-inch polyethylene tubing, 2 fire hydrant assemblies, 300 square yards of asphalt trench patching, and performance of additional and incidental work as called for in the Plans and Specifications. Schedule 2 includes, but is not limited to, all labor, materials, and equipment necessary to construction approximately 400 cubic yards of over-excavation, 300 tons of aggregate base, 2800 square yards of cold plane pavement removal, 650 tons of asphalt pavement, and 1 concrete ADA double curb ramp.