TOTAL SMALL BUSINESS SET-SIDE
This project includes the construction of a new paved parking lot consisting of approximately 75 parking spaces, a kiosk for Arizona Trail information, a public restroom, and the improvement of Sabino Canyon Park Road to accommodate approximately 21 new on-street parking spaces, an asphalt surface rehabilitation for approximately half a mile, and the installation of a 5-foot-wide pathway as part of the Arizona Trail. The project improvements will provide a new paved surface, roadway excavation, retaining wall construction, tree clearing, ditch construction/reconditioning to improve drainage, installation of culverts, a new public bathroom, and the installation of new street signage and pavement marking.
PRINCIPAL WORK ITEMS:
20401-0000 Roadway Excavation: 7,000 CUYD
25902-0000 Soil Nail Retaining Wall: 8,200 SQFT
30202-2000 Roadway Aggregate, Method 2: 1,800 TON
40301-0100 Asphalt Concrete Pavement, Type 1: 1,800 TON
60202-0600 36-Inch Equivalent Diameter Arch Pipe Culvert: 180 LNFT
60901-1700 Curb Concrete, 18-Inch Depth: 1,200 LNFT
60906-1000 Gutter, Concrete (Ditch): 750 SQYD
61501-0800 Sidewalk, Concrete: 1,100 SQYD
63501-0000 Temporary Traffic Control: LPSM
64603-1000 Fixture, Vault Toilet: 2 EACH
ANTICIPATED SCHEDULE:
Advertisement – July 2025
Award – September 2025
NTP – September 2025
Contract Completion – May 2026
The estimated price range of the project work is between $5 million and $10 million.