The Contractor shall provide sewage pumping and removal services at Fairchild AFB Clear Lake Resort. All service must comply with federal, state, and county rules and regulations to ensure environmentally compliant handling and proper disposal of the contents of the two (2) above ground sewage tanks at Clear Lake.
Amendment 001, published 7/16/2025, establishes a site visit on Monday, 21 July 2025 at 10:00 AM, and publishes questions and answers.
Amendment 002, published 7/21/2025, incorporates a revised Wage Determination and publishes questions and answers from the site visit held on 7/21/2025.
Amendment 003, published 7/29/2025 publishes questions and answers received from contractors.
Amendment 004, published 7/31/2025, publishes additional question and answer received from a contractor.
Amendment 005, published 8/12/2025, extends the quote deadline from 4 August 2025 at 10:00 AM PT to 12 August 2025 at 10:00 AM PT.
Amendment 006, published 8/12/2025, extends the quote deadline from 12 August 2025 at 10:00 AM PT to 13 August 2025 at 1:00 PM PT