Norfolk Naval Shipyard (NNSY) intends to award a Firm Fixed Price (FFP) Single Award Contract for the Fire Watch/Tank Watch Touch Labor Support. The required items are for commercial items prepared in accordance with the information in FAR part 13.5.
The requirement will be solicited as a 100% total Small Business set-aside. The North American Industry Classification Standard (NAICS) code applicable to this procurement is 336611. The small business size standard is 1300 (# of employees). The Product Service Code is J998.
The tentative period of performance for this acquisition is anticipated to begin August 15, 2025 through August 14, 2026.
ALL QUESTIONS SHOULD BE SUBMITTED BY JULY 4TH, 2025 BY 4:00PM EST.
RESPONSES TO QUESTIONS WILL BE POSTED BY JULY 10TH, 2025 BY 4:00PM EST.
Attachments are as follows:
Attachment 1 - Solicitation
Attachment 2 - Performance Work Statement
Attachment 3 - Addendum FAR 52.212-1
Attachment 4 - Addendum FAR 52.212-2
Attachment 5 - OPSEC plan
Attachment 6 - Contractor Capacity
Attachment 7 - DD 254
Attachment 8 - Wage Determination
Attachment # 9 - CDRL A001
Attachment # 10 - CDRL A002
Attachment # 11 - CDRL A003
Atttachment # 12 - CDRL A004
Attachment # 13 - CDRL A005
Attachment # 14 - CDRL A006
Attachment # 15 - CDRL A007
Attachment # 16 - CDRL A008
Attachment # 17 - QASP
Attachment # 18 - Questions/Answers
Solicitation has been amended. Please see in attachments questions and answers.
Solicitation and Performance of Work have been amended. Have added CDRL's as attachments.
Solicitation was amended to add correct solicitiation number.
Performance of Work statement was updated and attachment 3 and 4 the addendums were updated as well.
Amended Solicitation to provide answers to questions, updated attachments 1, 3, and 4, added QASP, and extending the solicitation due date to July 22, 2025 at 9:00am EST.
CLARIFICATION FOR ONE OF THE Q&A'S - QUESTION 23 - PREVIOUS Q&A
Question 23 - Attachment 3 Addendum FAR 52.212-1, Section 3.3, states that a resume is required for the Supervisor position. Will the Government confirm that only one resume is required for this role?
Government answer 23 – A minimum of 1 supervisor resume is required with contractor’s proposal. Subsequent submissions shall be delivered each week until 100% manning is achieved for supervisor requirement (7).
CLARIFICATION TO THE ORIGINAL ANSWER - 1 supervisor resume is required for the proposal. Additional supervisor resumes will be submitted each week (after contract award) until full manning is achieved.
This contract requires 7 supervisors in total. All 7 supervisor resumes should be submitted once full manning is achieved.