***********************************************************************
THIS IS TO IDENTIFY THE CONTRACTORS SELECTED TO MOVE TO PHASE 2 FOR THIS ACQUISITION. THE THREE CONTRACTORS ARE AS FOLLOWS:
BRISTOL BUILDING CONSTRUCTORS, LLC
RED POINT CONSTRUCTION, LLC
STG PACIFIC, LLC
***********************************************************************
This is a Design Build project to design and replace the existing four 1,500 kW standby generators and associated electrical equipment that provide primary power to the Eielson Air Force Base (EAFB) Power Plant Building B6203. The two bulk fuel storage tanks are to remain but are required to be inspected and a status report provided, detailing any concerns, issues and deficiencies. The bulk fuel tank fuel gauge equipment is not functioning and must be replaced. The signage for the generators and bulk fuel storage tanks must be replaced.
Contractor must maintain a minimum of 4,500kW (standby rated) power and 4,095kW (Prime rated) power available for the site and power plant from April 15th through September 15th. The contractor must maintain a minimum of 3,000kW (standby rated) power and 2,730kW (Prime rated) power available for the site and power plant from May 1st to July 31st. All other times of the year the contractor is not allowed to shut down a generator. 30-day notification of anticipated electrical shutdowns are required. The contractor must provide construction phasing plan, schedule, and assumptions in the Engineering Considerations and Instructions for Field Personnel (ECIFP) Report and within the design drawings and specifications.