1.0 SCOPE OF WORK: For the end item the contractor shall furnish all facilities, parts, materials,
equipment and services, required to inspect and, if necessary, restore to serviceable condition. Services to
be performed will not be essential in a crisis situation. Work consists of one of four efforts: Test,
teardown, and evaluation (TT&E) only; TT&E and Minor Repair; TT&E and Major Rebuild.
1.1 TEST, TEARDOWN, AND EVALUATION: The contractor shall perform visual, mechanical
and electrical testing of the end item, reusable or replacement component parts, and materials
according to the schedule in the contract to determine the condition of the end item. Upon
completion of this task, all of the components of the end item requiring repair or replacement
will be identified by part number, NSN (if applicable), nomenclature, and location in the
assembly. This information will be reported in writing to the Procurement Contracting Officer
(PCO)/ Defense Contract Management Agency (DCMA) Administrative Contracting Officer
(ACO) and, if necessary, a category of repair will be negotiated. The price of repair for the end
item will be firm-fixed based on this negotiated repair level. If no further repair is required, the
asset must be returned in serviceable like new condition.
1.2 MINOR REPAIR: (FFP) Minor repair is a repair that does not require total disassembly of the
end item or replacement of major subcomponents. A minor repair candidate typically requires
external adjustments or rework to meet all the electrical specifications in accordance with the
Technical Order Test Procedure and mechanical dimensions in accordance with the outline
drawing. It would include repair or replacement of damaged or missing minor external parts as
required. Test each end item IAW the specifications for P/N’s as listed in the contract schedule.
If minor repair is initiated and it is found that, to return the end item to serviceable condition that
the level of repair must increase to a major repair, the DCMA Government representative
(ACO/PCO or QAR) will be notified and give the notice to proceed to the major repair category.
1.3 MAJOR REPAIR: (FFP) Defined as an end item that is beyond the minor repair category to
the extent that the end item is to be disassembled or reconstituted. This could be due to
extensive mechanical damage, extensive disassembly to access or replace subcomponents and/or
replacement of major subcomponents. As with minor repair, the end item will be tested IAW the
specifications and Technical Order test procedures to verify correct Form, Fit, Function and
Interface of the P/N’s listed in the contract schedule.
Below listed item(s) will be shipped to contractor to repair:
Item Description NSN Part Number
Trigger Amplifier Assembly 5996-00-572-1617 345D585G01
This PWS establishes the minimum work requirements to return the end item(s) to a serviceable but like new condition.