PROJECT: Upper Silver Creek Trail Bridge Replacement
Stanislaus National Forest, CA
Total Small Business Set-Aside
IAW FAR 36.204 Disclosure of Magnitude of the Construction Project - between $100,000 and $250,000
Important Notes:
Refer to complete continuation pages for bid schedule, scope, specifications, exhibits, and all other information and terms.
Section A, Paragraph A.2, page 5, has information regarding documents to submit with your proposal.
Section B, page 8, provides notes on the bid schedule and bid submission.
All Requests for Information (RFI's) shall be submitted to the Contract Specialist via email to Tanya.Torres@usda.gov, on the attached RFI form, no later than 24 January 2025, 1100 AM hours PST.
A FS organized pre-proposal site visit will not be held. In no event shall failure to inspect the site constitute grounds for a claim after contract award.