The purpose of Amendment 02 is for the following:
A. Incorporate Questions & Answers from the site visit.
B. Incorporate Airfield Paving Specifications A and Haul Route attachments.
C. Extend proposals due date from 11 Feb 2025 to 2:00PM EST 14 Feb 2025.
POINT OF CONTACTs FOR THIS SOLICITATION ARE:
TSgt Joshua Brooks/ Contracting Adm. Phone: 302-677-5232. E-mail: joshua.brooks.14@us.af.mil
Omelia Saunders / Contracting Officer / Phone: 302-677-5545 / Email: omelia.saunders.2@us.af.mil
ALL OTHER TERMS AND CONDITIONS REMAIN THE SAME
The purpose of Amendment 01 is for the following:
A. Change site visit from 8 Jan 2025 at 2:00PM to 23 Jan 2025 at 2:00PM. Please provide a completed ACL request (Attached) NLT 15 Jan to allow time for base access request to be approved.
B. Questions resulting from site visit must be submitted via email by 1:00 PM EST, 29 January 2025.
C. Proposals due no later than 2:00PM EST 11 Feb 2025.
The project consists of providing all labor, materials, and equipment necessary to repair a portion of Runway 14/32 pavement (see location below).
The project consists of providing all labor, materials, and equipment necessary to repair 2100 LF Runway 14/32.
A. Rotor mill an area 150 LF x 2100 LF to a depth of 2 inches.
B. Repave 150 LF x 2100 LF with 2 inches PG 76-22 binder FAA Mix in accordance with
UFC 3-260-02. Groove new pavement in in accordance with UFGS 32 01 18.71(Grooving of Airfield Paving).
C. Crack seal 4200 LF (2100 LF x 2) 25 FT wide shoulder areas
D. Restripe all demolished stripes/markings with retroreflective (Type 1 or Type III beads) & white paint. Markings consists of 11 - 120 LF long arrows.