Q&A 2
Is the goal with the volumetric calculations of the containments to certify them or just to inspect and conduct the volume calculations? (It is to inspect and provide calculations demonstrating the containment area has sufficient capacity in accordance with 40 CFR 112.)
Q & A
RE: Question for Solicitation W9128F25Q0010 DUG
- Attachment B has the facility taking the wash water/fuel mix.
- Will the liquid need to temporarily stored prior to the facility taking it?
- Will the Contractor need to pump the liquid, or will the facility have a vac truck for the Contractor to pump into?
- What specifically are the liquids (wash water/fuel mix) being moved into?
Answer: For API external inspections, the KTR doesn’t have to empty the tank.
DLA-Energy has requested USACE conduct API 653 External inspections at Dugway Proving Grounds, UT on Tanks 4056, 4057, 5660 & 5661 in accordance with all laws standards, federal regulations, as well as any state and local regulations and guidelines.
See attachments for more details.