Work under this requirement consists of a construction, removal, replacement, and repairs associated with roadway and airfield projects at Ft. Riley, KS, including removal, replacement and repair of existing subgrade, utilities, shoulders, curbs, gutters, sidewalks, and other real property common to roadway and airfield pavements. Work may also include minor “new construction”, to include construction of new roads, new sidewalks, or new parking lots, or seeding operations based on the seeding season outlined in the KDOT Standard Specifications Section 904 Table 904-1 (https://www.ksdot.gov/bureaus/burConsMain/specprov/2015specprov.asp) . Work will be provided under multiple firm-fixed-price task orders issued as provided in the parent IDC contract. Each task order may involve a variety of construction trades. The Contractor shall provide all materials, labor, equipment, tools, transportation, and ancillary items necessary to complete each project from conception to completion.
Amendment 0001 corrected the Period of Performance of Base year and option years to reflect the 6-month -8 extension of the current Road Maintenance Contract in SF 1442: Block 21.
- Base Year: PoP 01-JUL-2023 to 30-JUN-2024 was changed 01-JAN-2024 to 31-DEC-2024
- Option 1: PoP 01-JUL-2024 to 30-JUN-2025 was changed 01-JAN-2025 to 31-DEC-2025
- Option 2: PoP 01-JUL-2025 to 30-JUN-2026 was changed 01-JAN-2026 to 31-DEC-2026
- Option 3: PoP 01-JUL-2026 to 30-JUN-2027 was changed 01-JAN-2027 to 31-DEC-2027
- Option 3: PoP 01-JUL-2027 to 30-JUN-2028 was changed 01-JAN-2028 to 31-DEC-2028
Bidders shall acknowledge this amendment by completing blocks 15A-C of this SF30 and block 19 of the SF1442.
No other changes to the terms and conditions of this solicitation are made or implied.
Amendment 0002
1. Added Clause 52.204-27 Prohibition on a ByteDance Covered Application
2. Edited Clause 52.216-18 to adjust Period of Performance to reflect the -8 extension of the current contract
3. Added Exhibit H: Site Visit Sign-In Roster (12 JUL 23).
Amendment 0003
1. Post Answers to Site Visit Questions (Labeled Exhibit I - Site Visit Questions Answered 2023-07-20 in Attachments)
2. Post Changes to Exhibit A - Bid Form (Labeled Exhibit A - Bid Form (Rev 1) in Attachments)
3. Correction to Attachment label to reflect W911RX-23-B-0001-0003, previous attachments were incorrectly labeled as W911RX-23-B-0003, W911RX-23-B-0003-0001, and W911RX-23-B-0003-0002.
Amendment 0004
1. Post Answers to Site Visit Questions (Labeled Exhibit I - Site Visit Questions Answered 2023-08-10 in Attachments)
2. Post Changes to Exhibit B – Summary of Work (Labeled Exhibit B - SECTION_01_11_00 Summary of Work Revised 2023-08-10 (Rev 1) in Attachments)
Bidders shall acknowledge this amendment by completing blocks 15A-C of this SF30 and block 19 of the SF1442.
No other changes to the terms and conditions of this solicitation are made or implied.
Amendment 0005
1. Extend the Bid Opening from 21 August 2023 at 2:00 PM CST to 29 August 2023 at 2:00 PM CST
2. Post Changes to Exhibit A - Bid Form (Labeled Exhibit A - Bid Form (Rev 2) in Attachments)