Purpose of project to provide electrical service from existing adjacent building to new two-story modular office spaces.
Site Visit: 10:00 AM ET Wednesday 19 Oct 2022 (preferred) or upon request. Regret cannot extend quotation due date 26 Oct 2022.
Register separately with both the NUWC Security and the NUWC Contracts Departments.
See Sections A, I, J, and L.
Provide new 225A/3P Eaton/Cutler-Hammer Series C molded case circuit breaker.
Provide new 2-1/2" EMT mounted above ceiling grid. Concrete core drilling required through exterior wall. Intermediate NEMA-1 pull/junction boxes.
Provide new 2-1/2" GRC; intermediate galvanized steel NEMA-4X pull/junction boxes.
Provide new 4-4#/0 and 1-4# EG.
Provide new interior data/comms junction box, 16" x 16" x 16", mounted above ceiling grid.
Provide new 2-1/2" GRC.
Project delivery 150 days after contract award (estimated to be on or about 1 Nov 2022).