Question:
Does the solicitation require "bid bonds"
A . No, only a payment bond will be required after award.
Does the solicitation require a “to be completed Not Later Than” date? Lead times on windows will likely put this into Nov-Dec or later. Is installation by 30 Apr 23 acceptable?
A. The Period of Performance is 30 days from issueance of Notice to Proceed. Weather and material delays will be taken into concideration and more time will be given if needed.
What is the O&M information on the B3129 CC section doors? Would you be able to provide cut sheets of exact style and finish?
A.
Per the SOW: For matching purposes, information on the doors currently installed in the work area is provided below. This is not a sole-source request by the Government. Details should be contractor verified:
Graham Wood Doors by Assa Abloy
Cherry veneer, plain sliced, book matched, best finish match to be determined by the contractor
M2G lip moulding for lites
¼” glazing for lites
GB16 blocking profile: top, bottom, and 1 lock block
For matching purposes, information on the blinds currently installed in the work area is provided below. This is not a sole-source request by the Government. Details should be contractor verified:
Bali Lightblocker Micro
½” aluminum slat
Color: Gray Haze #983
Is modifying the existing doors allowable? I.e.: are we allowed to cut the openings and install new window in lieu of replacing the slabs.
A. Yes, modification of existing doors is acceptable so long as there is a clean profession finish to the product.
Contractor will furnish all labor, supplies, parts, transportation, tools, equipment, and facilities necessary to perform work required to restore operations in accordance with the Statement of Work (SOW). See Combo with Attachments.
In accordance with AFARS 5132.702(a)(ii)(B), “Funds are not presently available for this acquisition. No contract award will be made until appropriated funds are made available.”