The purpose of Amendment 1 is to answer questions and extend RFQ close date. Period of Performance: What is the period of performance for (delivery & fully operational) contract completion? 180 days After receipt of award complete install. Facility: is facility ready for install when equipment arrives? Yes Terminal Sever: Will VA Biomed provision the additional VM (Nutanix) to their existing ICCA VM platform. Yes, see revised SOW Terminal Sever: Is the requirement to configure the additional terminal server to work with ICCA? No, See revised SOW. Is this an add on add on implementation of ICCA Philips requirement? no Hardware/software update/upgrade installations, add on schedule: The add on can be completed during business hours without service interruption, is this ok? Yes, See revised SOW. Min 2 days staff training: do you need Clinical Go Live Support? Yes. See revised SOW Is there a requirement to add Patient monitoring to the ED? No, See revised RFQ. RFQ close date is extended to 8/18/22 EST @1300.