Albeni Falls Dam Spillway Recoating and HSS Weld Repairs, Oldtown, Idaho. All work on the 11 spillway gates is expected to be completed within the required 1,085 days period of performance. This period of performance starts with a base of three (3) spillway gates, with the remaining eight (8) as options as funding becomes available. The successful Offeror is required to accomplish all on-site work in the Scope of work (SOW) during the Dam’s four-day work week and 10-hour days. Much of the work will occur offsite and will not fall under those restrictions. Exceptions will be considered at the Contracting Officer’s discretion. In addition, only one gate at a time can be removed at a time.