** AMENDMENT A00001 UPS Battery Upgrade West Haven Connecticut Contractor Questions and Government Responses ** Question 1. Do you have a loading dock to receive all material? Answer 1. Load center 1 would have somewhat easy access to load from road, there is a side door that can be opened, or the vendor might be able to bring materials in through new load center 1a. Infill has an outside door that the vendor can drive to/near and load from there. Should be no issues getting materials in and out of these locations. Question 2. Can you store equipment if received early? Answer 2. Both locations should have a space to store materials if anything load center 1 has enough room for both. Question 3. Please provide make, model, serial # along with pictures of existing charger system that you want replaced? Answer 3. See Pictures below