This Solicitation is a Request for Quote, utilizing simplified acquisition procedures, for a firm fixed priced construction purchase order.
The USDA ARS requires that all labor, supervision, tools, and materials be provided to construct concrete Foundations, and to erect a pre-engineered building structure (the structural steel and metal skin for the Hilco steel buildings is on site. This project shall be accomplished at the USDA Agricultural Research Service Dale Bumpers Small Farms Research Center (USDA ARS DBSFRC), 6883 South State Highway 23, Booneville, Arkansas. All work shall be performed in accordance with the terms, conditions, drawings, and specifications contained in the solicitation documents.
A single organized site visit has been scheduled for Tuesday, 5/17/2022 at 10am CST.
Meet at- Building 1
USDA, ARS, Dale Bumpers Small Farms Research Center
6883 S. State Hwy 23
Booneville, AR 72927
Contact: Larry Huddleston
(479) 675-3834
larry.huddleston@ars.usda.gov
For the site visit, we ask the following: The names of any visitors, and whether or not they are US citizens (if not, they should bring a passport)
Quotes must be received not later than 2:00p.m. CST Monday, May 31, 2022.
Quote must be emailed to:
Shalunda Mix, Contract Specialist
USDA ARS SEA AAO
shalunda.mix@usda.gov
QUOTE MUST BE ANNOTATED AS SUCH AND REFERENCE THE SOLICITATION NUMBER. Please include a detailed breakdown of price with various cost elements (e.g. materials, sub-costs, controllers, etc.). Additional quote instructions can be found in Section L.
SIZE OF PROJECT: In accordance with FAR 36.204, the estimated price range is Between $25,000 and $100,000.
All questions pertaining to this solicitation, including questions that arise during the site visit, must be submitted to shalunda.mix@usda.gov by 2:00p.m. CST, Thursday, May 19, 2022. Questions that are not submitted in writing or that are not submitted by May 19, 2022, may not receive a response. Questions/answers discussed at the site visit will not be binding on the resultant contract unless submitted