Specifications include, but are not limited to: Installation of medium voltage pad mount switches. The switches will provide preferred/alternate feeds to various campus buildings and isolation capabilities. These switches will be installed on the existing electrical distribution system at selected locations. Provide site modifications and infrastructure to facilitate the installation of pad mount equipment, ductbanks and water infiltration mitigation at the power plant, as indicated on site civil plans, as provided with the DCAMM RFP. Contractor shall have restricted use of Project site for construction operations during construction period. Contractor's use of Project site is limited by Owner's right to perform work or to retain other contractors on portions of Project. Contractor shall be responsible for the protection and maintaining all adjacent utilities on site. Any damage incurred on utilities at the site shall be immediately remedied by the contractor, to DCAMM’s satisfaction.