Specifications include, but are not limited to: 4.3.2 Demolition a. The contractor will be responsible for obtaining a demolition permit from the city of Dubuque prior to commencing any work. b. The contractor will be responsible for demolition, removal, and proper disposal of all structure and contents of the existing building(s) located at 1509-1511 Bluff Street c. The contractor will be responsible for demolition and removal of all slabs, foundation walls, footings, and all underground structures. d. The contractor will be responsible for removal of all accessory structures including but not limited to sheds and carports e. The contractor will be responsible for all costs of transport and proper disposal of all demolition debris resulting from the project 4.3.3 Utility Disconnects a. The contractor will be responsible for identifying, locating, coordination and cost of all utility disconnects, capping and removal to the utility main. b. Sewer line to be scoped and a water-tight plug installed at the property line into clean, sound pipe using one of the following: i. Neat Cement: Provide at a ratio of 14 pounds of cement per 1 gallon of water. ii. Bentonite: Graded bentonite, bentonite pellets, or bentonite grout. iii. Sand Cement Grout: Provide at a ratio of 1 sack of cement, equal volume of masonry sand, and not more than 6 gallons of water. iv. Concrete: Provide a Class A, Class B, or Class C mix meeting the requirements of Iowa DOT Materials I.M. 529. 4.3.4 Temporary Facilities a. The contractor will be responsible for all temporary features and facilities necessary to successfully complete the project – to include, but not limited to, portable restrooms, site fencing, site security, etc. 4.3.5 Certifications and permits a. The contractor will be responsible for obtaining all certifications and permits necessary for completion of the project from the appropriate regulatory agencies. 4.3.6 Salvage & Reuse of Materials a. Unless referenced otherwise in an addendum which will be provided at the mandatory pre-bid conference, the contractor shall take ownership of all scrap/salvage materials. b. No materials from the project are proposed for reuse by the City.