Specifications include, but are not limited to: The Contractor will expose bare mineral soil on 30% percent of each unit’s area (except unit 22). The Contractor shall repair all existing facilities, such as, but not limited to, roads, erosion dips, barriers, and drainage facilities, if damaged or removed by the Contractor. Landing piles that have been burned will be re-piled or scattered at the discretion of the Contract Supervisor. Unit 20 & 21 are accessed utilizing a Temp. Spur Road. This road was tank-trapped and water-barred post-harvest and is not drivable currently. The Contractor will need to open the road system back up for operations and then return the road to the condition originally found as directed by the Contract Supervisor (minimal work to obtain).