Specifications include, but are not limited to: The Hampstead School District (HSD) is soliciting bids for the removal of a 10,000 gallon underground storage tank (oil) and the installation of a new 5,000 gallon aboveground storage tank (oil). Contractor will work closely with Mark Anotina Designs who was hired by the HSD to design the new system and who will work on soil assessment acvities. 1. Contractor shall "pre-mark" the area for the excavaon and comply with all Dig Safe Regulaons. 2. Contractor shall comply with all laws, rules, and regulaons of the State of New Hampshire Department of Environmental Services and any other agency that oversees the removal of underground fuel oil storage tanks. Permit fees and requirements shall be borne by the contractor. 3. Contractor shall install a safety fence around the job site during removal and installaon. Contractor shall also install safety fencing for roadway access.