Specifications include, but are not limited to: 10 D701.010.0018 CS Pipe, 18-inch 61 Linear Foot 20 D701.010.0024 CS Pipe, 24-inch 898 Linear Foot 30 D701.010.0042 CS Pipe, 42-inch 520 Linear Foot 40 D751.010.0048 Manhole, Type I, 48-inch 6 Each 50 D751.010.0072 Manhole, Type II, 72-inch 1 Each 60 D760.010.0030 Thaw Pipe, 1.5-inch 1,480 Linear Foot 70 G100.010.0000 Mobilization and Demobilization All Required Lump Sum Lump Sum 80 G130.010.0000 Field Office All Required Lump Sum Lump Sum 90 G130.090.0000 Engineering Communications All Required Contingent Sum Contingent Sum $9,420.00 Construction Surveying by the Contractor 100 G135.010.0000 All Required Lump Sum Lump Sum 110 G135.020.0000 Extra Three Person Survey Party 80 Hour 120 G200.010.0000 Contractor Quality Control Program All Required Lump Sum Lump Sum Contractor Safety Plan Compliance Document 130 G210.010.0000 All Required Lump Sum Lump Sum 140 G300.010.0000 CPM Scheduling All Required Lump Sum Lump Sum 150 G310.010.0000 Public Updates All Required Lump Sum Lump Sum 160 G700.010.0000 Airport Flagger All Required Contingent Sum Contingent Sum $52,000.00 170 G705.010.0000 Watering for Dust Control 400 Mega Gallon Underground Cable #8 AWG, Copper, 5kV FAA Type C, L-824 180 L108.010.2008 15,078 Linear Foot 190 L108.030.0006 #6 Bare Copper Ground Conductor 16,335 Linear Foot 200 L108.070.0000 Ground Rod 19 Each 210 L108.180.0000 Temporary Jumper 10,000 Linear Foot 220 L110.050.1004 Rigid Steel Conduit, 4-inch 311 Linear Foot 230 L110.080.1002 HDPE Conduit, 2-inch 6,573 Linear Foot 240 L110.130.0002 Multi-Way Duct in Concrete (2 conduits) 447 Linear Foot 250 L110.240.0000 Drywell 9 Each 260 L115.010.0000 Electrical Manhole 2 Each 270 L125.040.0000 Taxiway Edge Light, L-861T 74 Each