Specifications include, but are not limited to: Provide all labor, services and materials necessary for the construction of 3,154 lineal feet of 16″ water main, 121 lineal feet of 10″ water main, 35 lineal feet of 8″ water main, and 332 lineal feet of 6″ water main installed by open cut construction methods, including: pavement removal; trench excavation; water main pipe and fitting materials and installation; connection to existing water mains; water service connections; abandonment of existing water mains; pipe bedding; trench backfill; valves and valve vaults; fire hydrant assemblies including fire hydrant and auxiliary gate valve; pavement replacement; site restoration; traffic control; water main pressure testing and disinfection; and all other work necessary for a complete and functional water main replacement installation as shown, specified, or required.