Specifications include, but are not limited to: Furnish labor, materials, and equipment necessary to excavate existing concrete sidewalks, concrete curbing, driveway approach, and concrete ramps as indicated on Construction Drawings. Install new concrete sidewalks, concrete curbing, driveway approach, and ADA-compliant concrete ramps per Construction Drawings. Place new ladder-style crosswalk striping as shown on Construction Drawings. Striping shall be “Preformed Traffic Markings, Type V” and meet all requirements set forth in Section 663 of the specifications. Re-establish all areas of disturbance and areas damaged during construction process (including but not limited to) grass areas between sidewalks and street, and edge of existing pavement adjacent to work area. Seed and mulch all disturbed areas. The contractor shall work on the project site between the hours of 7:00 AM and 7:00 PM.