Specifications include, but are not limited to: This RFP is being issued as part of the City’s Emergency Procurement procedure to repair unsafe sidewalk conditions for the City of Harvey. The RFP is for eliminating two vaulted sidewalk areas in downtown Harvey at 175th E. 154th Street and 190 E. 154th Street; The vaulted sidewalk was exposed in recent sidewalk construction. Once discovered, the areas were left undisturbed. Surface openings at both locations allow visual inspection of the void and basement access. The scope of work shall include the following: • Remove existing broken sidewalks • Construct a two-brick thick wall at the basement access opening after removal of wood framing • Close any additional basement wall openings as necessary to contain gravel backfill • Backfill void with suitable subgrade gravel material • Install 4” concrete sidewalk • At 175th E 154th ST, install single concrete step at each access door