Specifications include, but are not limited to: The N 48th Water Main Replacement work shall be completed in two (2) phases as defined in these special provisions. While some work within Phase 2 may start prior to the completion of Phase 1, any work that causes disruption to the traffic within Phase 2 must be approved by the City’s Project Manager. Phase 1 – Madison Ave to Gladstone Street Work in Phase 1 shall include setup of temporary water bypass and service, CIPP setup and installation, new water main and hydrant installation, testing and reconnection of services. The Contractor will be allowed a full closure of N 48th Street to complete the Work within Phase 1. The contractor will be allowed 90 consecutive calendar days to complete this Work. Failure to meet this time frame shall result in liquidated damages to be assessed in accordance with the Lincoln Standard Specifications. During Phase 1, the Contractor will be allowed a westbound closure of Adams Street at 2 separate timeframes. 14 consecutive calendar days will be allowed to perform work related to isolation of the main. 14 consecutive calendar days will be allowed for cross and valve replacement once the lining is complete. During Phase 1, the Contractor must maintain at least one lane of southbound traffic between Adams Street and Madison. All Work, within the southbound lane, to reconstruct the storm water drainage and water main work in N 48th St. @ Cleveland may not begin until after June 1, 2023. Work within this area must be coordinated with the paving contractor (Proj 705555) so that all paving is complete and open to traffic by August 14, 2023.