Specifications include, but are not limited to: The work for the CHAMPLAIN AVENUE WATER MAIN REPLACEMENT shall consist of, but not be limited to, the complete and satisfactory construction of installation of: - 1,800 LF of 6” Dia. DI Water Main - 660 LF of ¾” Copper Water Services - 530 CY Aggregate Base (MDOT 703.06 Type A) - 850 CY Aggregate Subbase (MDOT 703.06 Type D) - 540 Ton of 12.5mm HMA Surface Course - 720 Ton of 19mm HMA Base Course - 6,300 SY of Pavement Removal Work will include the installation of a new water main and services within the entirety of Champlain Avenue, and ~180-ft of water main in Surry Lane, as indicated on the bid plans. The existing pavement within Champlain Avenue & Surry Lane will need to be removed and repaved with base & finish surfaces to the full street width. Temporary water services during construction will be required during new main installation. Coordination with the Water District for requisite shut-downs will be required.