Specifications include, but are not limited to: Provide all labor, materials, and equipment necessary to perform the waterline extension project at the Cheney State Park; 1. Contractor Construction Staking Lump Sum Lump Sum ; 2. Mobilization Lump Sum Lump Sum ; 3. Traffic Control Lump Sum Lump Sum ; 4. Clearing and Grubbing Lump Sum Lump Sum ; 5. Erosion Control Lump Sum Lump Sum ; 6. Seeding Lump Sum Lump Sum ; 7. Connect to Existing Garden Plain Water System 1 Each ; 8. Garden Plain Meter Pit Vault with Piping and Meter Lump Sum Lump Sum ; 9. Garden Plain Backflow Vault with Piping Lump Sum Lump Sum ; 10. 4" HDPE Waterline (DR11)(In Place) 15,278 Lin. Ft. ; 11. 4" HDPE Waterline (DR11)(Bore by HDD) 455 Lin. Ft. ; 12. KDWP Meter Pit Vault with Piping and Meter Lump Sum Lump Sum ; 13. Connect to Existing KDWP Water System 1 Each ; 14. 8" MJ Gate Valve with Valve Box 1 Each ; 15. 4" MJ Gate Valve with Valve Box 3 Each ; 16. 6" Concrete Load Transfer Structure 1 Each