Specifications include, but are not limited to: The 84th Street Rehabilitation Project shall be constructed in three (3) segments as defined in these special provisions. The phases do not have to be completed in order. If the Contractor has enough crews to support more than one segment concurrently, they may do so. The construction phasing for the three (3) segments is as follows: Segment A Limits: Work in segment A shall consist of all concrete work activities within the south leg of the ‘O’ Street intersection (Sta. 175+17) for northbound and southbound traffic as well as asphalt work from Sandalwood (including the intersection) to the south side of ‘O’ Street. Segment B Limits: Work in segment B shall consist of all concrete work activities within the north leg of the O Street intersection (Sta. 176+00) through approximately 400 feet north of College Park (Sta. 185+00) and asphalt work activities up to the south leg of Vine Street. It also includes the repairs located on the south side of the O Street intersection for southbound traffic. Segment C Limits: Work in segment C shall consist of all concrete work activities at the Vine Street intersection (Sta. 199+00 through approximately Sta. 205+00) and asphalt work activities up to the north end of project limits.