Specifications include, but are not limited to: he Contractor shall construct this project beginning late Winter/ early Spring 2023. Contractor shall have total of 585 calendar days from the Beginning of Work date to achieve Final completion of this project. It is anticipated that the Contractor will receive a Notice to Proceed on or before February 1st, 2023. Contractor may elect to pothole utilities between Notice to Proceed and Beginning of Work without charges of calendar days. Substantial completion shall be achieved by August 8, 2024. Determination of Substantial completion shall be subject to the City’s Project Manager’s approval. Substantial completion shall be defined as all roadway construction being complete, all lanes open to traffic, storm sewer construction complete, all sidewalk/bike path construction complete, all temporary construction signs and barricades removed, all permanent pavement marking and signing complete, all roadway lighting complete and operational, final grading complete and all punch list items completed to the satisfaction of the City’s Project Manager.