Specifications include, but are not limited to: Disconnection and lock out of the natural gas and electrical connections Draining the system as necessary Disconnection of hot water piping, drains and stack connections Removal of all connections that will not be required by the resulting system Removal and proper disposal of the failed/outdated boiler Installation and connection of new shut off valves Reconnection of hot water piping, drains and stacking connections Insulating new hot water piping Reconnecting natural gas and electrical connections Installation of stack condensate drains (if applicable) Installation of new filters Replacement of existing pump motors (if necessary) Installation and interconnection of necessary sensors and controls Installing new piping from the equipment drain and stack connection drains to the condensate neutralization kit, and to nearest floor drain. Piping shall be at least one full size larger than a connection Filling system as necessary Starting system and confirming system functionality Balancing of hot water flow as required by local code