Specifications include, but are not limited to: 1. Notify Project Coordinator within 24 hours of plugging commencement. 2. Move in and rig up to existing 6 ⅝” casing. Pull 2” tubing. 3. Run in hole with work string to total depth (TD). Fill hole with fresh water. Gel hole to 1000'. 4. Set cement plug 4100' - 3800'. Pull work string, wait on cement (WOC). Tag plug, add cement if needed. 5. Pull 13 joints 6 ⅝” casing. Run in hole with work string to 2100’ and set cement plug 2100’ – 2000’. Pull work string, and WOC. Tag plug, add cement if needed. 6. Pull remaining 6 ⅝” casing. Run in hole to 1800’, then set cement plug 1800’ – 1700’. WOC, tag plug. 7. Pull work string to 1500’, then set cement plug from 1500’ to 1400’. Pull work string, WOC. 8. Run in hole with work string, set cement plug from 1200’ to 1100’. WOC. 9. Run in hole with work string to 600’. Set cement plug 600’ – 500’. WOC, tag plug. 10. Pull 10’ casing. Set cement plug from 400’ – 300’. WOC, tag plug. 11. Set cement plug from 200’ to surface. 12. Set monument. Reclaim site.