Specifications include, but are not limited to: HOT MIX ASPHALT PAVEMENT: Construct one or more courses of plant-produced Hot Mix Asphalt (HMA) pavement on an approved surface, to the lines, grades, and depths shown on the Plans. Warm Mix Asphalt may be used in lieu of conventional HMA. If the Contractor proposes WMA all provisions of this Section are in effect with the exception of a reduction in temperature may be allowed to produce and construct the asphalt concrete consistent with the WMA technology approved.; CULVERTS AND STORM DRAINS: This work includes the installation of High Density Polyethylene (HDPE) Liner for Storm Drain into culverts identified on the Plans.; Use the slip-lining method. The Contractor shall provide a slip-lining supervisor with experience on at least ten successful pipe slip-liners within the past 5 years. Prepare a work plan and submit to the Engineer for approval at least ten days before beginning the work.