Specifications include, but are not limited to: 5. Contractor shall trench as needed from the electrical room to the Conex box. Actual footage to be determined at the bid walk. 6. Contractor shall install a traffic rated utility box for access if needed at a later date. Exact location to be determined at bid walk. 7. Contractor shall install two (2) extra 1" conduits in the trench, one terminating at the newly installed traffic rated utility box. One will continue through to the interior of the Conex box as a spare if needed at a later date. 8. Contractor shall install a ground rod for the Conex box according to code. 9. Contractor shall back-fill, compact, and replace any concrete or asphalt removed during trenching. Asphalt joints and surfaces in area of excavation shall be sealed after installation. 10.Contractor shall remove all debris and packing material from the job site daily. 11.Contractor shall provide an electrical diagram that fully illustrates the work to be done and the existing conditions for State Fire Marshal (SFM) approval. Refer to the Submittal section, below, for further details. 12.Upon approval by SFM of the electrical diagram, contractor shall attend a preconstruction meeting. 14.Contractor to provide a one (1) year warranty on workmanship as well as the manufacturer’s warranty on all components installed.