Specifications include, but are not limited to: The extent of work on this project is the furnishing of all labor, equipment, and materials for the construction of improvements in West Des Moines generally described as follows: Paving of approximately 715’ of 76th Street between Aspen Drive and Ashworth Road including 2,915 CY of excavation, 2,560 SY of 7-inch thick reinforced PCC pavement, 3,040 SY of both subgrade preparation and 6-inch thick modified subbase, 1,215 LF of 6-inch subdrain, 340 LF of 15-inch RCP, 5 storm sewer structures, 775 LF of water main with assorted fittings, 1,375 LF of 7-way duct bank for fiber optic cable, 1,575 LF of conduit for fiber optic cable, 3 fiber optic cable vaults, and other miscellaneous associated work.