Specifications include, but are not limited to: There is one 120 ft. High Mast Tower to be removed under this project. The tower shall remain in place and in working order as long as possible as determined by the project manager. The tower complete with all its components including winch housing, lowering system and luminaires, will become the property of the contractor and must be removed from the project site Completely remove the existing tower foundation, including reinforcing steel and anchor bolts, to a minimum depth of thirty inches below grade: backfill excavation with clean soil and compact the soil to the density of the surrounding soil. Abandon unused conduit and cable in place. All rubble and waste resulting from the foundation removal shall be taken from the project.