Specifications include, but are not limited to: This project includes the installation of crack seal and seal coat of approximately 33,500 square yards of the Runway '15-33' asphalt pavement and the remarking of the runway. This project also includes the installation of new electrical improvements on Runway ’15-33’. These improvements include new LED runway edge light fixtures that shall be installed on existing bases and new LED signs shall be installed on new sign bases. This project includes a new homerun ductbank and vault upgrades for new dedicated circuits for Runway '15-33' and Runway ‘9-27’. There will be approximately 1,600 LF of new duct bank installed as part of this project along the south side of Taxiway ‘D’, complete with electrical handholes. The scope of work for the project also includes installation of additional electrical items. A new beacon on a new tilt down pole, will be installed to replace the existing beacon that has served its useful life. Two (2) new LED high mast lighting poles with multiple fixtures per pole, will be installed north of the Transient Apron. The infrastructure (conduit and handholes) for the high mast lighting was previously installed. Two (2) lighted wind cones will be installed on the Runway’33’ end of Runway ’15-33’ and the primary wind cone, located at the intersection of Runway ’15-33’ and Taxiway ‘D’ will be replaced