Specifications include, but are not limited to: a) Site Plan and Chiller Yard: after installation of chilled water piping and concrete yards for new chillers, Contractor shall re-grade all disturbed areas in the direction of the overall existing site drainage and provide new sod over such areas.; b) Ceiling work: ensure that demolition scope of work required for the removal of the existing MEP systems and the installation of new MEP systems above the existing ceiling includes the temporary removal of existing ceiling tiles/grid, light fixtures, fire alarm devices, speakers, life safety devices, etc. ; a) Add the following Structural Sheet to Table of Contents: i) S2.0 – RTU Plan; b) Section 232123 – Hydronic Pumps: i) For all outdoor mounted pumps provide the following: (1) Hot Dipped galvanized pump bases including motor saddles. Bases that are bolted together are not acceptable.; (2) Tnemec epoxy coating for additional environmental protection