Specifications include, but are not limited to: a. Warehouse 1 i. General Contracting 1. Install kleats to support overhead roll up door on south side of building; 2. Install kleats to support overhead roll up door on west side of building; 3. Frame in door on north side of building, insulate, and sheet exterior of opening; 4. Remove overbuilt wood floor, abandoned plumbing lines and other obstructions and dispose of materials; 5. Construct a four-foot-wide ramp in garage; 6. Seal east side man door and insulate. ii. Overhead Door Install 1. One 6’ wide insulated roll up, chain driven overhead door to replace a double man-door; 2. One 12’ wide insulated roll up, chain driven overhead door to replace double sliding bay doors. b. Warehouse 2 i. General Contracting 1. Remove and discarding of existing insulation on lid of building; 2. Remove existing skylights and sheet roof with galvanized metal roofing and mastic; 3. Install R13 fiberglass batts throughout ceiling area covered with 6-mil fire rated poly, secure with screws and washers; 4. Enclose, insulate, and seal man door back of warehouse 2; 5. Install kleating and heath for 12’x9’-6” R/O.