Specifications include, but are not limited to: 1. Only one paving operation is allowed at one time, excluding hand placed paving, unless otherwise approved by Resident. 2. Lane closure length will be kept to the minimum required for the shift’s operations, not to exceed the maximum allowed by contract. 3. The Contractor shall plan operations so that the Resident will have sufficient advance notification to provide the necessary inspection and testing. Sufficient notification is considered 48 hours. 4. There shall be a 24 hours transition period between switching to or from daytime and nighttime work. The contractors shall give the Department 48 hours notice before switching to or from daytime and nighttime work. 5. The contractor’s Traffic Control Plan shall address construction practices and schedules that will be implemented to minimize vehicle, pedestrian, and bicycle disruptions. 6. The contractor may elect to work at night provided they obtain written permission from the municipalities impacted. 0130 606.1306 31” W-BM GR, MID-WAY SPLICE TANGENT TERMINAL EA 4.000 ; 0140 606.1308 BURIED-IN-SLOPE GUARDRAIL END, MID-WAY SPLICE EA 1.000 ; 0150 606.353 REFLECTORIZED FLEXIBLE GUARDRAIL MARKER EA 6.000 ; 0160 610.08 PLAIN RIPRAP CY 20.000