Specifications include, but are not limited to: Edge mill 1.5 inch of existing asphalt from face of curb to a distance adequate to provide proper tie-in with in the specified length and according to the location key. b. Milling may be required on streets that are “overlay only” at driveways, around inlets, etc. c. Milling may be required on streets that are concrete at driveways, around inlets, at tie in’s, etc. d. Contractor is required to place 0.5 inch hot laid bituminous asphalt stratch/leveling course in the stated areas after the pavement removal is completed. e. Before placement of 1.0 inch hot laid bituminous asphalt a roller pass must be established for City personnel to determine adequate compaction. If batch number changes then another roller pass must to be established. Contractor is responsible for providing compaction testing to establish roller pass. f. Place 1.0 inch hot laid bituminous asphalt wearing course in the stated areas after application of stratch/leveling course is completed