Specifications include, but are not limited to: he project will be divided into two parts. The road segments for Part 2 are included in the contract documents but have not yet been identified. Part 2 will consist of approximately 70 centerline miles and will be identified at the pre-construction meeting. All work for Part 1 may begin on April 18, 2022and shall be completed by October 28, 2022,allwork for Part 2 may begin on September 12, 2022and shall be completed by October 28, 2022.Delays in completion beyond that date shall result in liquidated damages levied against the Contractor by Elkhart County. The damage charges shall be five hundred dollars ($500) per calendar day beyond the above stated date and any intermediate completion dates noted in the specifications.