Specifications include, but are not limited to: removal of existing TPO roofing, as well as temporary relocation of rooftop and wall-mounted accessories such as mechanical unit, ventilation pipes, conduit, drains and downspouts, etc. Contractor to furnish and install new (20 year) TPO roofing including additional insulation, accessories, and slope build-up as required in the contract drawings, as well as installation of new scuppers and fascia at roof edge and overhangs. Within the scope of this project is mitigation and repair of cracks in vertical CMU and CIP concrete walls by use of epoxies and silicone sealants. After remediation, the base bid includes a painted finish at exterior walls – some locations are to receive a fluid-applied weatherproofing under rigid insulation and a Metal Wall Panel and Plank system with integral rainscreen barrier. Windows, doors, soffits, and storefront to receive paint, flashing, sealants, as indicated in the drawings.