Specifications include, but are not limited to: Supply and install 8x16 PTMW detector hut; contractor shall provide all pre-wiring as required. Hut shall be installed as shown in the ARRC provided engineering documents titled “ARC_039516D_final plan” (Attachment 1) and “ARRC Anderson Detector Hut Pad” (Attachment 2) field fit as needed. • Supply and install all new concrete junction boxes as needed to complete all cable pulls; • Supply and install all 4” schedule 80 PVC conduit or SDR11, sweeps, and couplings to complete upgrades in the ARRC provided site plan. Smaller sized conduit may be used if prior approved by ARRC; o All conduit and cable shall be buried 24”to 36” deep below final top side grade; o Complete duct proofing on every conduit run; o Dig warning tape should be installed where feasible.; Signal, Electrical, & Grounding Work • Supply and install ground rods and bare copper wire for ground halo around the hut.; • Supply and install all new service conductor from the meter base to the new detector hut.; • Install all ARRC and contractor supplied signal cabling from the new house as shown in ARC_039516D_final plan (Attachment 1). All wire pulls shall provide slack in the j-box as close as possible to the detectors for future needs. Splicing of conductors will not be accepted unless approved by ARRC in writing.; • Install supplied Salient and Wabtec detector equipment per manufacturer’s specifications