Specifications include, but are not limited to: \1. The State of NH will provide access to the property for all dismantle and salvage work. 2. The railroad track section within the scope of work is approximately 2.18 miles in length, 11,510 ft. 3. Dismantle and salvage any present rail over 100 lbs and heavier, (i.e.112 lb/115 lb rail), joint bars. tie plates, and other misc 100 lbs and heavier other track materials to the NHDOT, deliver salvage material to rail yard in Whitefield, NH. 4. Dismantle approximately 11,510 lf of railroad track equaling 23,020 ft in length of 85 lb rail and salvage all joint bars and tie plates to the NHDOT, delivered to rail yard in Whitefield, NH. Select RR structures, including limited number of Points, Frogs, and other rerail material shall be marked for retention by NHDOT. Joint bars must be left in reusable condition. Bolts may be cut or unbolted, but not torched.